Search This Blog

Pages

Monday, 23 March 2015

INSPECTION TEST PLAN (ITP): BORED PILE WORK (CIVIL WORK)

TABLE OF CONTENTS

Section            Description

0.1        Inspection Categories

0.2        Notice(Request) of Inspection

1.0                              Pre-Activity Check

2.0                              Boring of Pile

3.0                              Pre- Pour Inspection – Trial and Production

4.0                              Concrete Reception and Placement

5.0                              Testing

6.0                              Cleaning

7.0                              Attachments

Attachment 1 – ITR-QGI–001-Rev1 REQUEST FOR INSPECTION/TEST

Attachment 2 – ITR-QCI–001 INSPECTION AND TEST REPORT FOR SURVEY

Attachment 3 – ITR-QCI–002-Rev1 INSPECTION AND TEST REPORT FOR BORED PILE

Attachment 4 ITR-QCI–003 BORED PILE STABILIZING FLUID TEST RECORD

Attachment 5 – ITR-QCI–004 LOAD TEST RECORD

0.1      Inspection Categories

The following inspection categories shall be used to identify the extent of inspection for each inspection activity within the ITP

I      Inspection items:
       It is the primary responsibility of Subcontractor and/or CONTRACTOR’s Quality Department to carry out the necessary inspection and test to assure conformance to the Contract requirements, drawings, specification and related codes and standards.

S     Surveillance
Monitor the status of work and materials and analyses of records on a periodical basis to ensure that specified requirements are being fulfilled. 
W    Witness
H    HOLD
Hold point (H) means a point, designated by prior stated agreement in the inspection and test plan(s), at which the performance of an activity must be stopped and put an hold until specified actions are completed.
R     Review
         Review results of inspection, examination or test.

0.2  Notice (Request) of Inspection

The Subcontractor shall submit to CONTRACTOR a ‘Notice of Inspection Request one (1) day before the inspection is to be carried out. The request shall contain information as follows:
·         Inspection item(s).
·         Responsibility Category. (as defined within the ITP)
·         Date, place and time of inspection.
·         Requirement for third party inspection (if any).
·         Any other relevant information.

The Subcontractor may proceed with the inspection activity at the specified time without the presence of CONTRACTOR or COMPANY for witness inspection unless a delay has been previously advised and agreed by either party.
·         The Notice of Inspection shall be sequentially numbered by the subcontractor in accordance with   SUT1-Z05-Q 00-4-001 ‘Numbering Procedure for Site Quality Documents’.


No.
Activity and Characteristic to be Checked
Reference Documents
(Codes/ Std/ Spec. / Proc.)
Acceptance Criteria
Verifying Document
Inspection Points
Sub-Con
CONTR.
SCC / RE / RTO
ITL
Pre-Activity Check







1.1
Verify method statement for piling is approval
Approval method statement
Method statement
R
R
R

1.2
Verification of Design Mix For Concrete
- Type of Concete
- Mix Propotion
- Slump
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
Approved /Accepted Concrete Design Mix by Engineer
Trial Mix Design Test Report
I
W
W

1.3
Concrete Design Mix & Method of Casting
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
As Per Project Spec. & Engineer Design / Instruction (C40 & C50)
Trial Mix Result Report & MS
I
R
R

1.4
Reinforcement Steel
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
Rebar Test Result Achieve requirement of specification / applicable standard T-High Yield, Rebar Grade 460
Rebar Test Report
I
W
W
I
1.5
Check for bench mark
Sembcorp Bench Mark.  New Bench mark(If necessary)
Confirmation of Sembcorp bench mark and Verified new datum.
ITR-QCI-001
INSPECTION AND TEST REPORT  FOR SURVEY
I
I
S

1.6
Verify pile design is approval.
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
Approval Construction Drawing
Approval Construction Drawing
I
R
R

2.0
Boring of Pile







2.1
Notification of Boring Work
-
Min. 1 day before commencement
ITR-QGI-001-Rev 1
REQUEST FOR INSPECTION & TEST
I
R
R

2.2
Survey of Pile Location –             Trial and Production
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
Location Plan : Coordinate ±75mm, Elevation, Horizontal position
ITR-QCI-001
INSPECTION & TEST REPORT FOR SURVEY
I
S
S










2.3
Verification of Casing
-  Drilling Accecories diameter
-  Casing diameter
-  Verticality of Casing
-  Top casing level
-  Setting out position

Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
BS 5400 – Grade 300, TH’K 6mm Min.
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
W
S

Veriticality of Casing
1/200 for CBP; 1/75 for foundation pile
Setting out position

+/- 25m for CBP; +/- 75mm for foundation pile
2.4
Monitoring Boring Progess
-  Rate of Penetration / Drilling
-  Monitoring Drilling in Soil or Rock (Change in tools from Soil to Rock Where Applicable)
-  Verticality of Machinery

Method of Statement
SUTO-ALL-C08-4-002 to 006
As per Project Specification.
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
ITR-QCI-002-Rev-1
BORING RECORD
I
W
I

3.0
Pre-Pour inspection  - Trial and Production







3.1
Pile Termination Check
-  Pile Toe has achieved as per Engineer Instruction
-  Adequate Cleaning of he Base
Approval For Construction Drawing
SUTO-ALL-C08-4-002 to 006
As per Project Spec. & AFC Drawing
Disturbed/Softened soil shall be removed
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
W
S(SCC)
H(RE/RTO)

3.2
Rebar Cage Check
-  No. of main rebar
-  Size of main rebar
-  Spacing of links
-  Size of Links
-  Splicing length
-  Diameter of the cag
-  Installation of Rebar Cage
-  Lifting Point detail


Approval For Construction Drawing
SUTO-ALL-C08-4-002 to 006
As per Project Spec. & AFC Drawing Checklist Item.





ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
W
W

3.3
Stabilizing Fluid
-  Density
-  Viscocity
-  pH Test
-  Sand Content
Method of Statement
SUTO-ALL-C08-4-002 to 006
Property to be measure
Fresh mixed fluid
Prior to placing steel cage
Test method
ITR-QCI-003
BORED PILE STABILIZING FLUID TEST RECORD
I
W
W

Density
<1.06 g/ml
<1.15 g/ml
Mud density balance
Viscosity
40-65s
NA
Marsh cone
pH
8-11
8-11
pH indicator paper
Sand Content
≤4%
≤4%
Wet seiving
4.0
Concrete Reception and Placement







4.1
Check of concrete grade as per approved Mix. Design and Q’ty
Approval For Construction Drawing
SUTO-ALL-C08-4-002 to 006
Verify the correct concrete Mix design and grade used and Q’ty as per estimated volumn. Cube Test result acceptance criteria
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
W
S

4.2
-  Slump
-  Temperature
-  Tremie pipe length
-  Concrete level
-  Over cast

-  Mix design /DO
-  Mix Design/ DO
-  Mix Design
-  Sounding
-  Method Statement

As per Project Spec. & AFC Drawing



ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
W
   R(SCC)
W(RE/RTO)

4.3
Sampling of cube test
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
As per Engineer Instruction
Lab. Test  Report
I
W
R
I
4.4
Concrete Quantity Check

N.A
Design & Actual Quantity
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
R
R

4.5
Check time between Truck leaving batching plant and Pouring
Approved Design Mix
SUTO-ALL-C08-4-002 to 006
Time not to exceed.
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
I
S
S

5.0
Testing







5.1
Vertification of Test Method
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
Conforming  to requirement of specification and approve Test Method
Method Statement
I
R
R

5.2
Vertification of Pile testing Laboratory
SUTO-ALL-C08-4-002 to 006
Independent test Lab. Approved by company verify theTest & measuring Instrument calibrated
Calibration Report
I
R
R
I
5.3
Pile Load Test / Type & Quantity
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
*. Static Load Pile Test : 1% of Total Production Pile or One pile test for each pile typeOne pile test for each pile type
*. Dynamic Test Pile : 5% of Production Piles all test pile
*. Integrity Test Pile : All working Pile
Test Report
ITR-QCI-004
Load Test Record

I
W
H

5.4
Pile Test Acceptance Criteria for Working pile
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
Allowable Settlement:
Short Term = 15mm &
Long Term = 25mm
Test Report
I
R
R

5.5
Submission of test results to company
SUTO-ALL-C08-4-002 to 006

Test Report of Lab.
I
R
R

6.0
Cleaning







6.1
Confirm Concrete debris, etc
SUTO-ALL-C08-4-002 to 006
Visual
Visual
I
S
S


LEGEND : ITL : Independent Testing Laboratory   I : Execution of Inspection and Test      R: Review    S : Surveillance     W : Witness    H : Hold Point

3 comments:

  1. Thanks for this. I really like what you've posted here and wish you the best of luck with this blog and thanks for sharing. Piling inspection

    ReplyDelete