TABLE
OF CONTENTS
Section
Description
0.1
Inspection Categories
0.2
Notice(Request) of Inspection
1.0
Pre-Activity Check
2.0
Boring of Pile
3.0
Pre- Pour Inspection – Trial
and Production
4.0
Concrete Reception and
Placement
5.0
Testing
6.0
Cleaning
7.0
Attachments
Attachment 1 – ITR-QGI–001-Rev1 REQUEST FOR
INSPECTION/TEST
Attachment 2 – ITR-QCI–001 INSPECTION AND TEST REPORT FOR SURVEY
Attachment 3 – ITR-QCI–002-Rev1 INSPECTION AND TEST REPORT FOR BORED PILE
Attachment 4 – ITR-QCI–003 BORED PILE STABILIZING FLUID
TEST RECORD
Attachment 5 – ITR-QCI–004 LOAD TEST RECORD
0.1
Inspection Categories
The following inspection categories shall be used to identify the
extent of inspection for each inspection activity within the ITP
I Inspection
items:
It is the primary
responsibility of Subcontractor and/or CONTRACTOR’s Quality Department to
carry out the necessary inspection and test to assure conformance to the Contract
requirements, drawings, specification and related codes and standards.
S Surveillance
Monitor the status of work and
materials and analyses of records on a periodical basis to ensure that
specified requirements are being fulfilled.
W Witness
As mandatory items of inspection,
examination, or test this stage shall be notified in advance by the
Subcontractor or CONTRACTOR’s construction department and shall be performed
under witness of the relevant Inspection Authority. However, work may proceed
if the relevant authority is not available at the required time.
H HOLD
Hold point (H) means a point,
designated by prior stated agreement in the inspection and test plan(s), at
which the performance of an activity must be stopped and put an hold until
specified actions are completed.
R
Review
Review results of
inspection, examination or test.
0.2 Notice (Request) of Inspection
The Subcontractor shall submit to CONTRACTOR a ‘Notice
of Inspection Request one (1) day before the inspection is to be carried out.
The request shall contain information as follows:
·
Inspection item(s).
·
Responsibility Category. (as
defined within the ITP)
·
Date, place and time of
inspection.
·
Requirement for third party
inspection (if any).
·
Any other relevant information.
The Subcontractor may proceed with the inspection
activity at the specified time without the presence of CONTRACTOR or COMPANY for witness inspection unless a delay has been previously advised and agreed by either
party.
·
The Notice of Inspection shall
be sequentially numbered by the subcontractor in accordance with SUT1-Z05-Q 00-4-001 ‘Numbering
Procedure for Site Quality Documents’.
No.
|
Activity and Characteristic
to be Checked
|
Reference Documents
(Codes/ Std/ Spec. / Proc.)
|
Acceptance Criteria
|
Verifying Document
|
Inspection Points
|
|||||||
Sub-Con
|
CONTR.
|
SCC / RE / RTO
|
ITL
|
|||||||||
Pre-Activity Check
|
||||||||||||
1.1
|
Verify method statement for piling is approval
|
Approval method statement
|
Method statement
|
R
|
R
|
R
|
||||||
1.2
|
Verification
of Design Mix For Concrete
- Type of Concete
- Mix Propotion
- Slump
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Approved /Accepted Concrete Design Mix by Engineer
|
Trial Mix Design Test Report
|
I
|
W
|
W
|
|||||
1.3
|
Concrete
Design Mix & Method of Casting
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
As Per Project Spec. & Engineer Design / Instruction (C40 & C50)
|
Trial Mix Result Report & MS
|
I
|
R
|
R
|
|||||
1.4
|
Reinforcement Steel
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Rebar Test Result Achieve requirement of specification / applicable
standard T-High Yield, Rebar Grade 460
|
Rebar Test Report
|
I
|
W
|
W
|
I
|
||||
1.5
|
Check for bench
mark
|
Sembcorp Bench Mark. New Bench
mark(If necessary)
|
Confirmation of Sembcorp bench mark and Verified new datum.
|
ITR-QCI-001
INSPECTION AND TEST REPORT FOR SURVEY
|
I
|
I
|
S
|
|||||
1.6
|
Verify pile design
is approval.
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Approval Construction Drawing
|
Approval Construction Drawing
|
I
|
R
|
R
|
|||||
2.0
|
Boring of Pile
|
|||||||||||
2.1
|
Notification of Boring Work
|
-
|
Min. 1 day before commencement
|
ITR-QGI-001-Rev 1
REQUEST FOR INSPECTION & TEST
|
I
|
R
|
R
|
|||||
2.2
|
Survey of Pile Location – Trial and Production
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Location Plan : Coordinate ±75mm, Elevation, Horizontal position
|
ITR-QCI-001
INSPECTION & TEST REPORT FOR SURVEY
|
I
|
S
|
S
|
|||||
2.3
|
Verification of Casing
- Drilling
Accecories diameter
- Casing diameter
- Verticality of
Casing
- Top casing level
- Setting out
position
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
BS 5400 – Grade 300, TH’K 6mm Min.
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
|
I
|
W
|
S
|
|||||
Veriticality of Casing
|
1/200 for CBP; 1/75 for foundation pile
|
|||||||||||
Setting out position
|
+/- 25m for CBP; +/- 75mm for foundation pile
|
|||||||||||
2.4
|
Monitoring Boring Progess
- Rate of
Penetration / Drilling
- Monitoring
Drilling in Soil or Rock (Change in tools from Soil to Rock Where Applicable)
- Verticality of
Machinery
|
Method of Statement
SUTO-ALL-C08-4-002 to 006
|
As per Project Specification.
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
ITR-QCI-002-Rev-1
BORING RECORD
|
I
|
W
|
I
|
|||||
3.0
|
Pre-Pour inspection - Trial and
Production
|
|||||||||||
3.1
|
Pile Termination Check
- Pile Toe has achieved as per Engineer Instruction
- Adequate Cleaning of he Base
|
Approval For Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
As per Project Spec. & AFC Drawing
Disturbed/Softened soil shall be removed
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
|
I
|
W
|
S(SCC)
H(RE/RTO)
|
|||||
3.2
|
Rebar Cage Check
- No. of main rebar
- Size of main rebar
- Spacing of links
- Size of Links
- Splicing length
- Diameter of the cag
- Installation of Rebar Cage
- Lifting Point detail
|
Approval For Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
As per Project Spec. & AFC Drawing Checklist Item.
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
|
I
|
W
|
W
|
|||||
3.3
|
Stabilizing Fluid
- Density
- Viscocity
- pH Test
- Sand Content
|
Method of Statement
SUTO-ALL-C08-4-002 to 006
|
Property to be
measure
|
Fresh mixed
fluid
|
Prior to
placing steel cage
|
Test method
|
ITR-QCI-003
BORED PILE STABILIZING FLUID TEST RECORD
|
I
|
W
|
W
|
||
Density
|
<1.06 g/ml
|
<1.15 g/ml
|
Mud density
balance
|
|||||||||
Viscosity
|
40-65s
|
NA
|
Marsh cone
|
|||||||||
pH
|
8-11
|
8-11
|
pH indicator
paper
|
|||||||||
Sand Content
|
≤4%
|
≤4%
|
Wet seiving
|
|||||||||
4.0
|
Concrete Reception and
Placement
|
|||||||||||
4.1
|
Check of concrete grade as per approved Mix. Design
and Q’ty
|
Approval For Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Verify the correct concrete Mix
design and grade used and Q’ty as per estimated volumn. Cube Test result
acceptance criteria
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
|
I
|
W
|
S
|
|||||
4.2
|
- Slump
- Temperature
- Tremie pipe length
- Concrete level
- Over cast
|
- Mix design /DO
- Mix Design/ DO
- Mix Design
- Sounding
- Method Statement
|
As per Project Spec. & AFC Drawing
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
|
I
|
W
|
R(SCC)
W(RE/RTO)
|
|||||
4.3
|
Sampling of cube test
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
As per Engineer Instruction
|
Lab. Test
Report
|
I
|
W
|
R
|
I
|
||||
4.4
|
Concrete Quantity
Check
|
N.A
|
Design & Actual Quantity
|
ITR-QCI-002-Rev 1
INSPECTION
& TEST REPORT FOR BORED PILE
|
I
|
R
|
R
|
|||||
4.5
|
Check time between
Truck leaving batching plant and Pouring
|
Approved Design Mix
SUTO-ALL-C08-4-002
to 006
|
Time not to exceed.
|
ITR-QCI-002-Rev 1
INSPECTION & TEST REPORT FOR BORED PILE
|
I
|
S
|
S
|
|||||
5.0
|
Testing
|
|||||||||||
5.1
|
Vertification of Test
Method
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Conforming to requirement of specification and approve
Test Method
|
Method Statement
|
I
|
R
|
R
|
|||||
5.2
|
Vertification of Pile
testing Laboratory
|
SUTO-ALL-C08-4-002 to 006
|
Independent test Lab.
Approved by company verify theTest & measuring Instrument calibrated
|
Calibration Report
|
I
|
R
|
R
|
I
|
||||
5.3
|
Pile Load Test / Type
& Quantity
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
*. Static Load Pile
Test : 1% of Total Production Pile or One pile test for each pile typeOne
pile test for each pile type
*. Dynamic Test Pile
: 5% of Production Piles all test pile
*. Integrity Test
Pile : All working Pile
|
Test Report
ITR-QCI-004
Load Test Record
|
I
|
W
|
H
|
|||||
5.4
|
Pile Test Acceptance
Criteria for Working pile
|
Approval Construction Drawing
SUTO-ALL-C08-4-002 to 006
|
Allowable Settlement:
Short Term = 15mm &
Long Term = 25mm
|
Test Report
|
I
|
R
|
R
|
|||||
5.5
|
Submission of test
results to company
|
SUTO-ALL-C08-4-002 to 006
|
Test Report of Lab.
|
I
|
R
|
R
|
||||||
6.0
|
Cleaning
|
|||||||||||
6.1
|
Confirm Concrete
debris, etc
|
SUTO-ALL-C08-4-002 to 006
|
Visual
|
Visual
|
I
|
S
|
S
|
|||||
LEGEND : ITL : Independent Testing Laboratory I : Execution of Inspection and Test R: Review S : Surveillance W : Witness H : Hold Point