SPECIFICATION AND STANDARD FOR STRUCTURAL STEELWORK: GENERAL PART 4- DESIGN


1.7.1         Connection Details

1.7.1.1      The Contractor shall design and detail the connections which are not shown in the Contract Drawings. The type of joint is to follow the form of the typical details shown on the Contract Drawings and is to be designed to carry loads, which shall be specified.

1.7.1.2      All details designed by the Contractor are to be substantiated by full calculations certified by a Singapore-registered Professional Engineer.




1.7.2         Temporary Works

1.7.2.1      The  Contractor  shall  design,  fabricate,  erect  and  remove  all  temporary  works pertaining to the structure.

1.7.2.2      A Professional Engineer shall be engaged for the design and supervision of the erection of all temporary works and he shall be responsible for ensuring the safety and stability of the structure during all stages of the construction.