1.10.1 General
1.10.1.1 All metal on metal welding shall be done in accordance with BS EN1011 and AWS
D1.1. Spot welding
of
cold-formed
steel sections
shall also
conform
to the requirements outlined in the above standard.
1.10.1.2 All butt welds shall be full penetrations unless noted otherwise.
All fillet welds shall
be 6mm
continuous unless noted otherwise.
All welds shall be chipped free of slag.
1.10.2 Welding Electrodes
1.10.2.1 Electrodes shall be of approved types conforming to AWS D1.1 and shall be kept in
a dry store in unbroken packets.
1.10.3.1 The general procedures for shop and site welds and other details shall be submitted
in
writing, in accordance with AWS D1.1, to SCI for approval
before fabrication.
1.10.4 Approval and Testing of Welding Procedure
1.10.4.1 The Contractor shall carry out welding procedure tests in accordance with AWS
D1.1, to demonstrate by means of a specimen on a steel representative of that to be
used that he can produce satisfactory welds with the proposed welding procedure.
1.10.5 Approval and Testing of Welders
1.10.5.1 The Contractor shall satisfy SCI that his welders are suitable for the work upon which they
are
employed.
Welders working to approved welding procedures shall satisfy the relevant requirements of AWS D1.1.
1.10.6 Measurement of Weld Sizes
1.10.6.1 The Contractor shall provide gauges necessary for the measurement of weld sizes.
1.10.7 Site Welding
1.10.7.1 No site welding shall take place unless shown in the Shop Drawings or
otherwise
approved. Where site welding is required or permitted the Contractor shall submit
details of staging, platforms and
weather protection for welders and materials. Site
welding shall be subject to all the requirements of welding as defined in this section of the Specification.
1.10.8 Quality of Weld
1.10.8.1 All welds shall be visually inspected as per AWS D1.1. All non-destructive testing
shall be as per AWS D1.1. Any
weld
with defects greater than
the maximum permitted as in the Code shall
be liable to rejection.
1.10.9 Frequency of Testing
1.10.9.1 Visual Inspection
All welds are to be visually inspected.
1.10.9.2 Selection of Welds to be Examined
1.10.9.3 Where there is
a requirement
for
less
than 100% examination,
the method
of selection of welds
to be
examined is to
be agreed
with the
Engineer before the commencement of work.
1.10.9.4 Where examination reveals unacceptable defects in a joint, two additional joints in
the
group represented by the joint are to be examined. If the results on these two additional joints are acceptable then the
original weld may
be repaired and re-
examined by similar means.
1.10.9.5 If the non-destructive examination of the two additional joints reveals unacceptable defects, examine each joint in the group.
1.10.9.6 The cost of testing, examining and repair of welds that fail to meet the specified
requirements shall
be borne by the Contractor.
1.10.9.7 Welded connections made on circular hollow sections
The interface on steel plates, steel sections and steel hollow sections which are to
be welded to circular hollow
sections shall be machine reamed so that the reamed edges match perfectly with the curvature of the CHS at the connections. Thermal cutting of the steel plates, steel sections and steel
hollow sections to produce the desired profile at the mating surfaces is not acceptable.
1.10.10 Inspection Authority
1.10.10.1
The examination of welds shall be carried out by approved personnel
from the
accredited laboratory engaged by the Contractor.
No comments:
Post a Comment