Search This Blog

Pages

Thursday 11 August 2016

Civil and Structural Piling Specification Part 1- INTRODUCTION

CONTENTS

1.     INTRODUCTION

2.     C4-10 BORED PILING

3.     C4-20 DRIVEN PILING

4.     C4-30 PILE TESTING


1    INTRODUCTION

This document presents the specifications for piling works to be used in the project. The specifications found herewith shall supplement SCI’s specification listed below and the Invitation to Bid (ITB) Appendix A: Facilities Description / Scope of Work document. Unless noted otherwise, the more onerous criteria or requirements specified between SCI’s specification and the ITB
Appendix-A document shall take precedence over the conflicting clauses found in this document.



SCI Specification & Standard Document No.

Rev.

Document Title

SUTO-ALL-C08-4-001

1

Specification and Standard: Demolition and Site Clearance

SUTO-ALL-C08-4-002

2

Specification and Standard: Earthworks and Excavation

SUTO-ALL-C08-4-003

1

Specification and Standard: Piling – Driven Piles

SUTO-ALL-C08-4-004

1

Specification and Standard: Structural Steelworks

SUTO-ALL-C08-4-005

1

Specification and Standard: Soil Investigation & Testing

SUTO-ALL-C08-4-006

1

Specification and Standard: Concrete

SUTO-ALL-C08-4-008

1

Specification and Standard: Pipe Rack Design Criteria



In the event that the specifications are not available in either the SCI’s or those found herewith, refer to the latest edition of the National Productivity and Quality Specifications published by SPRING Singapore. The specification list is non-exhaustive and will be expanded if the need arise.


2    C4-1 BORE PILING

CONTENTS                                                                                                              Page


1.
GENERAL
3
1.1
Scope
3
1.2
Related Sections
3
1.3
Standards and Regulations
3
1.4
Trade Preambles
4
1.5
Definitions
7
2.
PERFORMANCE REQUIREMENTS
8
2.1
Requirements for Design Verification
8
2.2
Performance Criteria for Piles Under Test
8
2.3
Permissible Damage Criteria for Existing Critical Structures or Services
8
3.
MATERIALS
9
3.1
Source of Materials
9
3.2
Drilling Fluid
9
3.3
Water
9
3.4
Concrete
9
3.5
Grout
9
3.6
Reinforcement
9
3.7
Temporary Casings
9
3.8
Permanent Steel Casings
10
4.
WORKMANSHIP
11
4.1
General Workmanship Requirements
11
4.2
Trial Bores
11
4.3
Boring Excavation
11
4.4
Use of Drilling Fluid
13
4.5
Cleanliness of Pile Bases
13
4.6
Reinforcement
14
4.7
Pile Casting
14
4.8
Backfilling Empty Boring
17
4.9
Grouting of Piles
17
4.10
Tolerances
18
4.11
Protection to Piles
19
4.12
Replacement of Piles
19
4.13
Cleaning Up
19
4.14
Non-Performance of Working Piles
19
4.15
Cutting Off Pile Heads
19
4.16
Noise and Disturbance
20
4.17
Final Survey and As-Built Drawing
20
5.
VERIFICATION AND SUBMISSIONS
21
5.1
Submissions
21
5.2
Inspection and Test Certificates
22
5.3
Tests
23
5.4
Compliance Testing of Drilling Fluid
23
5.5
Pile Testing
24
5.6
Records
25
.       GENERAL

Read with the General Requirements section, and all other contract documents.

1.1     Scope

This section covers the requirements for the construction of bored cast-in-place piles including:

a.       In-situ concrete piles b.       Micro piles

The piles may be used as foundations to support principally vertical loads, or may be used to forembedded retaining walls resisting principally horizontal loads.

1.2     Related Sections

Read this work section in conjunction with the relevant requirements of the other work sections as follows:

C1-20   Condition Survey and Monitoring

C2-10   Site Investigations

C2-50   Instrumentation and Monitoring

C4-30    Pile Testing

C3-10    Concrete Construction Generally

C3-20    Reinforcement

1.3     Standards and Regulations

1.3.1   Standards

Unless otherwise agreed by the Superintending Officer (SO), ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the SO, provided it can be demonstrated that the alternativStandards and Codes comply with the requirements  o the  standards specified.  AlStandards and Codes quoted arthe current version, unless specific year references are noted.

Singapore   Standards

SS 31  Aggregates from natural sources for concrete

SS 78: ParA16 Testing  Concrete Method  o determination  o compressive strength of concrete cubes

SS CP 4     Foundations

SS CP 65: Part 1  Structural use of concrete. Design and Construction

SS CP 79   Safety management system for construction worksites


Other Standards

API SpecificationDrilling Fluid13A 5th Edition

API-RP-13B-1 2nd   Standard procedure for field-testing water-based drilling fluid Edition BS 1305 Batch type concrete mixers

BS EN 1008                     Mixing water for concrete, specification for sampling, testing and assessing the suitability of water

BS 5228                           Noise and vibration control on construction and open sites

Par 1(1997)  Code  o practice  for  basi information  and procedures for noise and vibration control

Part 4 (1992) Code of practice for noise and vibration control applicable to piling operation

BS 5930                           Code of practice for site investigations

BS 7123                           Metal arc welding of steel for concrete reinforcement

BS 8004                           Code of practice for foundations

BS 8008                           Guide   to   safety   precautions   and   procedures   for   the construction and descent of machine-bored shaft piling and other purposes.

BS EN 1538                     Execution of special geotechnical work  Diaphragm Walls

In the event that the standards or Codes are revised or superseded, refer to the latest edition or the appropriate substitution for the relevant subjects.

1.3.2   Technical Reference

Refeto the following technical reference for guidance in carrying outhe works:

a.        BRE Digest 251 (1995) Assessment of damage in low-rise building.

b.        Construction IndustrResearch and Information Association, England (CIRIAReport 104 (1984) Design of retaining wall embedded in stiff clay.

1.4     Trade Preambles

1.4.1   Design Verification

Engage technically competent personnel with relevant geotechnical experience to SOs acceptanceto carry out:

a.        Verification of material excavated at the intended pile founding level as consistent with the design requirements.

b.        Design verification checks based on actual ground conditions to determine the required length of each pile and ensure that the specified working load and settlement criteria othe piles are achieved.

c.         Proposals to amend the design including compensating piles as necessary in the event that for any reasons the installed piles do not perform as intended.

d.        Proposals to amend the pilecap design of the building in the event that the piles are installed out othe permitted tolerance.

e.        Proposals as a response plan in the event that measures taken to control ground movement and vibration do not perform satisfactorily.

Take into account othe design requirements as set out in Clause 2.1 below.

Submit the design to the SO for acceptance. Design proposals in (c) to (d) are to be designed and endorsed by a PE (Civil).

Submit the CV of the personnel to be engaged for the above including the PE’s, for SOs acceptance.

1.4.2   Building Damage Assessment


Carry out Building Damage Assessment, if required by the project specification, on the effects of ground movement tthe neighboring properties due tthe works, for the purpose o establishing suitabl values for  ‘Alert and  Wor Suspension’ level for monitoring. Submito SO with endorsemenfrom a PE.

1.4.3   Coordination with Other Works

Co-ordinate with other contractors who may carry out other works at the same time at the site. Takinto account of site access, space occupation, safety and safeguarding of adjoining properties and each others works.

1.4.4   Condition Survey

Where applicable, prior to and upon completion of the site works, carry out a condition survey t adjacent  building i accordance  wit the  requirements  o section  C1-20 Condition Survey and Monitoring. Submit all records to the SO and adjacent property owners where directed.

Keep a copy of the survey report on site ready for inspection.

1.4.5   Instrumentation and Monitoring

Provide instrumentation to monitor the ground movement, vibration and condition of adjacent properties. Refer to Section C2-50, Clause 3.1, and the drawingfor the schedule of instrumentation required. If necessary or as required by the authorities, propose and provide additional instrumentation and monitoring for records.

Take cognisance of and co-ordinate with other contractors on site who may be carrying out  instrumentation  and  monitorin works  to  avoi duplication  of  installation  and readings.

For general requirements of the instrumentation and monitoring works refer to Section
C2-50.

1.4.6   Upholding of Adjoining Properties

Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the site through the duration othe works.

Adequately maintain roads and footpaths within and adjacent to the site and keep cleaof mud and debris.

1.4.7   Verification of Site Information

1.4.7.1   Site Surveys

Verify  and  be  satisfied  that  the  information  given  i the  existing  site  survey  plans provided are accurate. If necessary, engage a registered Surveyor to carry out additional site survey before commencing any work.

1.4.7.2   Additional site investigations

Carry out additional ground investigation where additional information is needed for the works or when directed by the SO. Carry out the works in compliance with Section C2-10 Site Investigation.

Carry out the boreholes progressively prior to commencement of the works in areas according tthe contractors construction programme. On completion of drilling, backfilthe boreholes with a suitable bentonite / cemenmix.

Submit the location and schedulfor the boreholes tSOs acceptance prior to carrying out the works. On completion, prepare the site investigation report and submit tthe Sfor acceptance.

1.4.7.3   Groundwater level


Verify the data on groundwater level from available ground investigation reports.

1.4.7.4   Contamination

Verify information on contamination identified or believed to be present on site.

In the event that contamination is either positively identified or suspected, draw to the attention  o all  personnel  working  on  site  together  with  the  need  to  take  any precautionary measures in handling contaminated materials, groundwater and obnoxious vapours frothe ground.

1.4.8   Existing Services Affected by the Works

Refer to Preliminaries and Conditions of Contract for the requirements to deal with existing services affected by the works.

1.4.9   Site Protection

Protect all equipment and working area using fencing or other methods as accepted.

1.4.10 Obstructions

I any obstructions  suc as  existing  fences structures,  footings,  boulders,  concrete blocks, pipes, drains, driveways or ramarencountered during excavation, submit proposals for theiremoval for the SO's acceptance.

1.4.11 Supervision of the Works

Engage a competent and suitably experienced site engineer to the SOs acceptance, to supervise the field works.

1.4.12 Quality Control Plan

Submit and work to a quality control plan as agreed with the SO. Refer to the General
Requirements section, clause 1.4.10 for guidance.

1.4.13 Safety

Provide safety precautions to comply with all current legislation and regulations, notably:

a.  Building Control Regulations

b.    Code of Practice for Traffic Control at Work Zone

c. Factories(Building Operations and Works of EngineeringConstruction)Regulations

d.        Workplace Safety & Health Act

e.        SS CP 79 Safety management system for construction worksites

f.         For works within LTA Railway Protection Zone, ensure the works comply fullwith Code of Practice for Railway Protection.

Additionally, comply also with the following:

a.        BRE Digest 251 (1995) Assessment of damage in low rise building

b.         BS 8008: Guide to safety precautions and procedures for the construction and descent omachine-bored shaffor piling and other purposes

1.4.14 As-Build Pile Surveys

Employ a Licensed Surveyor who is to be responsible for surveying pile locations and eccentricities and submit the as–build surveto the SO in format as directed within 14 days after the piles have been trimmed to the cut-off level.

1.5      Definitions


a.
Pile Dimensions
Piles dimension specified in pile layout drawing(s) / piling
schedule are the minimum acceptable dimensions
b.
Rock
Material classified as grade I to III in table 10 Scale of
weathering grades orock mass” in BS 5930: 1981.

No comments:

Post a Comment