Search This Blog

Pages

Monday 22 August 2016

Civil & Structural Piling Specifications Part 4- PILE TESTING part 2 of 3

4.
WORKMANSHIP
12
4.1
Schedule of Tests
12
4.2
Construction of Preliminary Test Pile
12
4.3
Load Testing: General
13
4.4
Load Test: Static Load Test Procedures
16
4.5
Load Test: Osterberg Load Test
20
4.6
Load Test: Lateral Load Test
21
4.7
Load Test: Dynamic Test
21
4.8
Integrity Tests: Proof Coring
22
4.9
Integrity Test: Non Destructive Tests (NDT)
23
4.10
Protection of Testing Equipment
24
4.11
Noise and Disturbance
25
5.
VERIFICATION AND SUBMISSIONS
26
5.1
General Submissions
26
5.2
Preliminary Test Piles
26
5.3
Results of Static Gravity and Lateral Load Tests
27
5.4
Results of Dynamic Load Tests
30
5.5
Results of Osterberg Cell Load Tests
32
5.6
Results of Pile Integrity Tests
33



4.        WORKMANSHIP

4.1      Schedule of Tests

Refer to drawings

For the purpose of establishing the number of tests required, the percentages given in the schedule relate to the total number of working piles on a contract. Round up part number of tests calculated based on the total number of piles.

4.2      Construction of Preliminary Test Pile

4.2. Method of Construction

Construct each preliminary test pile in a manner similar to that for the working piles, and by the use of similar equipment and materials. Install preliminary test piles in ground similar to that where the working piles are to be installed.

Provide extra reinforcement and concrete of increased strength as directed by the SO to ensure no premature structural failure during load tests.

4.2. Instrumentation for Preliminary Piles

Instrument the preliminary piles with 2 or 4 nos. of extensometers through the pile depth and a minimum of 2 nos. of vibrating wire strain gauges per level at various levels as shown in the drawings.

Fix the vibrating wire strain gauges and extensometer securely to the reinforcement cages of the piles, and maintain orientation in the direction of the movement to be measured, and protect from damage at all stages of pile construction.

4.2. Cut-off Level

Terminate the pile shaft slightly above the normal cut-off level or at a level required by the SO.

Extend the pile shaft above the cut-off level of working piles so that gauges and other apparatus to be used in the testing process will not be damaged by water or falling debris.

Where the pile shaft is extended above the cut-off level of a working pile in soil which would  influence  the  load  bearing  capacitof  the  pile,  install  a  sleeve  to  eliminate additional friction which would not arise in the working pile. Alternatively, if the friction above the designed cut-off level can be calculated with reasonable accuracy, a sleeve need not be used, take the calculated friction into account in assessing the load applied to the pile.

4.2. Pile Head Construction

4.2.4. Compression Test

For a pile that is tested in compression, form the pile head in a plane surface normal to the axis of the pile, sufficiently large to accommodate the loading and settlement measuring equipment and adequately reinforced or protected to prevent damage from the concentrated application of load from the loading equipment.

Ensure the pile head and/or cap is concentric with the test pile; check that the joint between the cap and the pile is not weaker than the pile.

Make sufficient clear space under any part of the cap projecting beyond the section of the pile so that, at the maximum expected settlement, load is not transmitted to the ground except through the pile.

4.2.4. Tension Test
For a pile that is tested in tension, provide means for transmitting the test load axially to the pile. Construct the connection between the pile and the loading equipment with strength equal to the maximum load which is to be applied to the pile during the test with an appropriate factor of safety on the structural design.

4.2. Uniformity of Pile Shaft

For bored test piles, ensure the pile is uniform in diameter along its entire shaft with overbreaks not exceeding 10% of its nominal diameter at any section.

Compute the percentage overbreak in the pile as the percentage excess between the concrete volume discharged per truck as indicated by the concrete delivery docket and the resulting concrete displacement in the bored pile based on the nominal size of the piles. Take the overbreak into account in the interpretation of test results or reject at the SOs direction.

4.3      Load Testing: General

In addition to the methods and procedures prescribed below, ensure that the load testing is in general conformance with the requirements of SS CP 4.

4.3. Testing Equipment

4.3.1. Stability

Ensure that when the hydraulic jack and load measuring device are mounted on the pile head, the whole system is stable up to the maximum load to be applied. Provide the means to enable dial gauges to be read from a position clear of the kentledge stack or test frame in conditions where failure in any part of the system due to overloading, buckling, loss of hydraulic pressure etc. will not constitute a hazard to personnel.

4.3.1. Test Pressure

Ensure that the hydraulic jack, pump, hoses, pipes, couplings and other apparatus to be operated under hydraulic pressure are capable of withstanding a test pressure of one and a half times the maximum working pressure without leaking.

4.3.1. Maximum Test Load

Check that the maximum test load or test pressure expressed as a reading on the gauge in use is displayed and all operators are aware of this limit.

4.3. Verification of datum

Prior to carrying out a pile load test and setting up of the load test equipment, survey to establish a datum for the pile head level relative to a permanent bench mark. Verify the pile level each time before a loading cycle to ensure that the pile is not loaded prior to being subjected to the test loads.

4.3. Reaction Systems

4.3.3. Compression Tests

Carry out  compression tests using kentledge, tension  piles  or  specially constructed anchorage. Do not use kentledge for tests on raking piles.

Where kentledge is to be used, support it on cribwork disposed around the pile head so that its centre of gravity is on the axis of the pile. The bearing pressure under supporting cribs is to be such as to ensure stability of the kentledge stack, and if necessary, provide a pile support system to the kentledge. Do not rest the kentledge directly on the pile head.

4.3.3. Tension Tests
Carry out tension tests using compression piles or rafts constructed on the ground. The use of inclined reaction piles, or rafts is not precluded, subject to the acceptance of the SO. In all cases, ensure that the resultant force of the reaction system is co-axial with the test pile.

4.3.3. Use of Working Piles

Do not use working piles as reaction piles without acceptance from the SO. Where used as reaction piles, measure their movement to within accuracy of 0.5 mm.

4.3.3. Use of Kentledge

Where kentledge is used for loading vertical piles in compression, the distance from theedge of the test pile to the nearest part of the crib supporting the kentledge stack in contact with the ground is to be not less than 3 times the diameter of the test pile and a minimum of 2m whichever is greater.

4.3.3. Tension Pile and Ground Anchors

Where tension piles or ground anchors are used,  ensure that  the  load  is  correctly transmitted to all the tie rods or bolts. Do not extend the rods by welding unless it can be ensured that the steel will not reduce in strength by welding. Ensure that the bond stresses of the rods in tension do not exceed normal permissible bond stresses for the type of steel and grade of concrete used.

4.3.3. Spacing of Vertical Reaction Piles

The centre to centre spacing of vertical reaction piles, including working piles used as reaction piles, from a test pile, is to be not less than 3 times the diameter of the test pile or the reaction piles or 2 m, whichever is the greatest. Where a pile to be tested has an enlarged base, apply the same criterion with regard to the pile shafts, with the additional requirement that the surface of the reaction piles is to be no closer to the base of the test pile than half of the enlarged base diameter.

4.3.3. Spacing of Ground Anchors

Where ground anchors are used to provide a test reaction for loading in compression, no part of the section of the anchor transferring load to the ground is to be closer to the test pile than 3 times the diameter of the test pile. Where the pile to be tested has an enlarged base, apply the same criterion with regard to the pile shaft, with the additional requirement that no section of the anchor transferring load to the ground is to be closer to the pile base than a distance equal to the base diameter.

4.3.3. Care of Piles

Ensure that the method employed in the installation of any reaction piles, anchors orrafts do not damage any test pile or working pile.

4.3. Measurement of Load

Measure the load by a load measuring device and by a calibrated pressure gauge included in the hydraulic system. Record readings of both the load measuring device and the pressure gauges. In interpreting the test data, regard the readings from the load measuring device as normal and use the pressure gauge readings as a check for gross error.

4.3.4. Calibration of Load Measuring Devices

Calibrate the load measuring devices before and after each series of tests, whenever adjustments are made to the device or at intervals appropriate to the type of equipment. Calibrate the pressure gauge and hydraulic jack together.

4.3.4. Adjustability of Loading Equipment
Check that the loading equipment is capable of adjustment throughout the test to obtain a smooth increase of load or to maintain each load constant at the required stages of a maintained loading test.

4.3. Measuring Movement of Pile Heads

4.3.5. Maintained Load Test

In a maintained load test measure the movement of the pile head by two of the methods in Clauses 4.3.5.3 to 4.3.5.5 using methods appropriate to vertical piles or raking piles, as required.

4.3.5. Constant Rate of Penetration (CRP) or Constant Rate of Uplift (CRU) Test

In a CRP or CRU test, use the method in Clause 4.3.5.4 or 4.3.5.5 below.

4.3.5. Levelling Method
An optical or any other levelling method by reference to an external datum may be used. Where a level and a staff are used, choose the level and scale of the staff to enable
readings to be made to within an accuracy of 0.5 mm. A scale attached to the pile or pile
cap may be used instead of a levelling staff. Establish at least two datum points on permanent objects or other well-founded structures or install deep datum points. Site each datum point so that only one setting up of the level is needed.

Ensure that Datum points are not affected by the test loading or other operations on the
Site.

4.3.5. Independent Reference Frame

An independent reference frame may be set up to permit measurement of the movement of the pile. The supports for the frame is to be founded in such a manner and at such a distance from the test pile, kentledge support cribs, reaction piles, anchorages and rafts that movements of the ground in vicinity of the equipment do not cause movement of the reference frame during the test which will affect the required accuracy of the test.

Check observations of any movement of the reference frame and check the movement of the pile head relative to an external datum during the progress of the test. In no case the supports are not to be less than three test pile diameters or 2 m, whichever is the greater, from the centre of the test pile.

Measure the pile movement by at least two dial gauges rigidly mounted on the reference frame that bear on surfaces normal to the pile axis, fixed to the pile cap or head. Alternatively, fix the gauges to the pile and bear on surfaces on the reference frame. Place the dial gauges in diametrically opposed positions and equidistant from the pile axis. The dial gauges are to enable readings to be made up to within an accuracy of
0.1mm. Use a scale ruler and levelling device to provide an independent measurement of the pile head movement.

Protect the reference frame from the weather.

4.3.5. Other Methods

Details of any other method for measuring the movement of pile heads may be submitted for acceptance.

4.3.5. Calibration of Dial Gauges

Calibrate the dial gauge used for the measurement of load by a SINGLAS accredited laboratory to the accuracy as required.

4.3. Continuous Testing
Once commenced, carry out any test to completion without stoppage unless otherwise agreed by the SO.

4.3. Completion of a Load Test

4.3.7. Measuring Equipment

On completion of a test dismantle and check all equipment and measuring devices and either store so that they are available for use in further tests or remove from the site.

4.3.7. Kentledge

Remove Kentledge and its supporting structure from the test pile and store so that they are available for use in further tests or remove from the site.

4.3.7. Ground Anchors and Temporary Piles

On completion of a preliminary test, cut off temporary piles 2 m below ground level, and make good the ground with accepted material.

Remove all ground anchors unless otherwise directed.

4.3.7. Preliminary Test Pile Cap

Break off the pile cap, if formed in concrete, dispose the resulting material off the site. If the pile cap is made of steel, cut it off and store so that it is available for use in further tests, or remove from the site.

Break down preliminary test piles to 2 m below original ground level or as required and backfill to the original ground level with suitable material.

4.3.7. Working Load Test Pile Cap

On  completion  of  working  load  test,  strithtest  pile  cap  if  in  concrete  unless otherwise agreed. Leave the pile in a state ready for incorporation in the permanent works and dispose the resulting material off the site.

If the pile cap is made of steel, cut it off and store so that it is available for use in further tests, or remove from the site as directed.

4.4      Load Test: Static Load Test Procedures

4.4. Ultimate Load Test by Maintained Load

Unless otherwise specified the maximum load which is to be applied in an ultimate load test is 3 times the specified working load. This test is only applicable to preliminary piles. The loading and unloading is to be carried out in stages as shown in the table below.


Ultimate Load Test Cycles

Load, Percentage of
Working Load
Minimum Time of Holding
(Minutes)
Load Cycle Number
0
-
1
25
60

50
60

75
60

100
24hrs

70
60

35
60


0
60

0
-
2
50
60

100
60

125
60

150
60

175
60

200
24hrs

150
60

100
60

50
60

0
60

0
-
3
50
60

100
60

150
60

200
60

225
60

250
60

275
60

300
24hrs

200
60

100
60

0
60

Following each application of load, hold the load for not less than the period shown or
until the rate of settlement is less than 0.1 mm/hr and slowing down. Calculate the rate of settlement from the slope of the curve obtained by plotting values of settlement versus
time and drawing a smooth curve through the points.

Proceed unloading for each stage after the expiry of the period shown in the table.

For any period when the load is constant, record time and settlement immediately on reaching the load and at approximately 15 min intervals for the 1st hr, at 30 min intervals between the 1st and 4th hr and at 1 hr intervals between the 4th and 12th hr after the application of the increment of the load.

Continue testing until the maximum test load has been reached or when the settlement exceeds 10% of the pile diameter.

4.4. Working Load Test by Maintained Load

Unless otherwise specified the maximum load to be applied in a working load test on a working pile is 2 times the specified working load. Carry out the loading and unloading in stages as shown in the table below.




NPQS
                                                                                                                                                                             C4-30 Bored Piling Piles


Working Load Test Cycles

Load, Percentage of
Working Load
Minimum Time of Holding
(Minutes)
Load Cycle Number
0
-
1
25
60

50
60

75
60

100
24hrs

70
60

35
60

0
60

0
-
2
50
60

100
60

125
60

150
60

175
60

200
24hrs

150
60

100
60

50
60

0
60

Following each application of an increment of load, hold the load for not less than the
period shown or until the rate of settlement is less than 0.1 mm/hr and slowing down. Calculate the rate of settlement from the slope of the curve obtained by plotting values of settlement versus time and drawing a smooth curve through the points.

Proceed unloading for each stage after the expiry of the period shown in the table. For any  period  when  the  load  is  constant,  recortime  and  settlement  immediately  on reaching the load and at approximately 15 min intervals for the 1st hr, at 30 min intervals between the 1st  and 4th  hr and at 1 hr intervals between the 4th  and 12th  hr after the application of the increment of the load.

4.4. Constant Rate of Penetration (CRP) or Constant Rate of Uplift (CRU)Test

The rate of loading is to be such that a CRP/CRU is maintained throughout the test as far as practicable. Propose the rate of movement of each pile to be tested for SOs acceptance prior to the start of the test.

Take readings of load, penetration or uplift and time simultaneously at regular intervals; choose the intervals such that a curve of load versus penetration or uplift can be plotted without ambiguity.

Continue loading until one of the following results is obtained. a.        the maximum specified test load is reached.
b.        a constant or reducing load has been recorded for an interval of penetration or uplift of 10 mm.

c.         a total movement of the pile base equal to 10% of the base diameter, or any other greater value of movement required has been reached.

Reduce the load in five approximately equal stages to zero load; record penetration or uplift and load at each stage and at zero load.

4.4. Combined  Working  Load  Test  and  Constant  Rate  of  Uplift  (CRU)  or
Constant Rate of Penetration (CRP) Test

When required, carry out a Working Load Test by maintained loading prior to a CRU or
CRP Test.

4.4. Quick Load Test Method

The testing procedure is to be in accordance with ASTM D1143.

Apply the load in increment of 10% to 15% of the proposed design load with a constant time interval between increments of 2.5 min unless otherwise agreed. Add load increments until continuous jacking is required to maintain the test load or until the specified capacity of the loading apparatus is reached, whichever occurs first, at which time stop the jacking. After a 5-min or otherwise agreed interval, remove the full load from the pile.

4.4. Abandoning of Tests

Abandon a static load test if any of the following occurs:

The specified material and workmanship requirements for loading and testing are not met for any reason.

If any test had to be discontinued due to:

i.          faulty jack on the gauge,

ii.         unstable support of the kentledge,

iii.        cracking in or damage to the pile cap, iv.        incorrect or disturbed datum,
v.         prejacking or preloading before commencement of test.

vi.        Any other causes deemed to affect the validity of the test results.

Disregard the results of abandoned tests. In the event of an abandoned test, carry out another test as directed by the SO.

4.4. Failure of Static Load Test

A static pile load test is deemed to have failed if the load-deflection performance criteria specified in the piling specification are not satisfied. Carry out remedial measures as stipulated in the piling specifications.

4.5      Load Test: Osterberg Load Test

4.5. Preparation of Pile

For bored piles, prior to concreting, clean the toe of pile and install O-cell. Attach the O- cell assembly, including O-cells, bearing plates, related hydraulically supply, tremmie pipes and instrumentation to reinforcing steel cage and lower them into the bored hole. Initially, position the bottom of the O-cell assembly about 600mm above the pile base. Use concrete with retarder to fill sufficiently high (at least 2m) above the O-cell assembly. Lower the pile re-bars cage and O-cell assembly slowly into the underlying concrete. Carry out the concreting as per standard/approved procedure.

For driven piles, cast the O-cell assembly, including O-cells, bearing plates, related hydraulically supply and instrumentation together with the pile. After the concrete have gained sufficient strength, drive the pile into the ground as per standard/approved driving procedure.

4.5. Maximum Test Loads

Unless otherwise agreed, the maximum test load in an Osterberg Cell Load is to be the ultimate capacity of a pile in either end bearing or side shear, or the maximum stroke of the O-cell.

4.5. Abandoning of Osterberg Load Tests

Abandon load test if any of the following occurs: -

The specified material and workmanship requirements for loading and testing are not met for any reason.

If any test has to be discontinued due to:

i.          faulty O-cells,

ii.         cracking in or damage to the pile, iii.        incorrect or disturbed datum,
iv.        prejacking or preloading before commencement of test.

v.          Any other causes deemed to affect the validity of the test results. Disregard the results of abandoned tests.
4.5. Failure of Osterberg Cell Load Test

An Osterberg Cell load test is deemed to have failed if the load-deflection performance criteria specified in the piling specification are not satisfied. Carry out remedial measures as stipulated in the piling specifications.

4.6      Load Test: Lateral Load Test

4.6. Lateral Load Test on Preliminary Piles

Design the reaction and testing system to apply a horizontal load on the preliminary pile. Check that the horizontal lateral load on the pile head is parallel to a pair of strain gauges already installed in the pile. Identify piles into which the inclinometer tube is required and submit to the SO for acceptance not less than 72 hours before the pile is concreted.

The testing procedures are to be the same as that for static load tests except that only one load cycle is required with each load increment to be held for 1 hour (mm) until the ultimate lateral load capacity or 300mm pile top deflection, whichever occurs first.

Monitor the strain gauges in the pile at every load step.

4.6. Lateral Load Tests on Working Piles

Undertake lateral load tests on an adjacent pair of bored cast insitu piles. Test by either jacking the piles apart or pulling them together.

Apply the test load at or within 0.5 metres of the pile cap soffit level. The test load is to be equal to the lateral working load of the pile. Measure pile deflections parallel to the direction  of  the  applied  load  such  that  the  movement  of  each  pile  is  measured  in absolute terms and not as a relative movement between piles. Check that dial gauges and load cells used are accurate to 0.1mm and 10kN for deflection and load measurements respectively.

4.6. Recording Deflection

Record deflection for every 12.5% of the test load during both loading and unloading. Where specified on the Drawings, record the rotation of the pile at the same increments. Carry out loading sequence in 2 cycles. At the first cycle, test the pile to 75% of the test load and then reduce to zero. At the second cycle, test to 100% of the test load and then reduce to zero.

4.6. Increase of Load

For both loading cycles, increase the load only if the rate of movement is less than
0.2mm in 20 minutes and subject to a minimum holding period of 20 minutes at the end of  each  incremental  increase.  The  minimum  holding  period  may  be  reduced  to  10 minutes if  the rate of  movement  is less than 0.1mm  in  10  minutes  for  every load increment previously applied on the first cycle during the second loading cycle. The minimum holding period is 3 hours at the maximum load for both the first and second loading cycle. The minimum holding period during unloading is 20 minutes at the end of each incremental decrease for both load cycles.

4.6. Failure of Lateral Load Tests on Working Piles

A pile or pile group under lateral load test is deemed to have failed if the lateral deflection or rotation at the pile cap soffit level exceeds the Serviceability Limit State (SLS) criteria at the test load. Carry out remedial measures as stipulated in the piling specifications.

4.7      Load Test: Dynamic Test

Carry out dynamic tests by companies accredited by SAC-SINGLAS only.

4.7. Preparation of Pile Heads

Prepare and level the pile head for fixing the testing instruments, such that consistent results are obtained. Ensure that the pile head is free of debris and other deleterious smaterial. Remove any loose material from the pile head to expose sound concrete, and ensure the head is horizontal over its complete cross-section.

4.7. Dynamic Load Testing Requirement

Piles may be tested during the entire driving process, at the end of driving or during restrike. Carry out computer analysis of the field measurements to obtain the pile resistance distribution and vertical load against displacement relationship.

Unless otherwise directed, conduct dynamic tests on all preliminary test piles which are to be statically load tested, to provide the basis and calibration for other dynamic load test results.

Provide a suitable hammer system able to mobilise the piles to a minimum of 2.5 times the specified working load for driven piles, and a minimum of 1.5 times the specified working load for bored piles. Check that the hammer system consists of an adequately heavy hammer with a controlled drop to limit the driving stresses in the pile. In general, the energy provided on to the pile during restrike tests is not to be less than that used to drive the pile initially.

4.7. Failure Criteria for Working Piles

Piles which are dynamically tested are deemed to have failed if the measured resistance of the pile is less than 2.0 times the specified working load or if any part of the test piles is damaged during driving or testing. Carry out remedial measures as stipulated in the piling specifications.

4.7. Damage Caused

Be responsible for any damage caused to the pile or dynamic test equipment, including transducers and cables, due to handling of the pile, objects falling from the pile frame or the pile hammer.



NPQS
                                                                                                                                                                             C4-30 Bored Piling Piles


4.8      Integrity Tests: Proof Coring

Check the quality of concrete in bored piles by vertical coring to at least 0.5 metre below the pile toe using a diamond coring barrel at an agreed location of the pile. Ensure that the core so produced is not affected by drilling disturbance and reflect the condition of concrete in the pile. The core is not to be less than 100 mm in diameter and is placed in suitable core boxes in the order of core recovery.

Complete coring work before the concrete in the pile has reached an age of 28 days to allow the cores to be tested at 28 days. Arrange for transport to the testing laboratory. Deliver the remainder of cores to a core store.

On completion of proof coring, grout the core cavity within and below a pile. The grout is to be of the same grade as the pile concrete, of a non-shrinkage type. Submit details o fthe proposed grouting method and mixes for acceptance 14 days prior to undertaking any such operation.

4.8. Acceptance of Proof Coring

Check the quality of cores produced against criteria as set out below. Piles, from which cores do not satisfy the given requirements, may be rejected at the discretion of the SO.

4.8.1. In Concrete

For this purpose, concrete is considered as being rock. Requirements for cores are as follows:

a.        Visually free from defects, such as contaminants and honeycombing. b.        100% Total Core Recovery (TCR)
c.        100% of Rock Quality Designation (RQD)

4.8.1. In Soil/Rock

Requirements for cores are:

a.        100% Total Core Recovery.

4.9      Integrity Test: Non Destructive Tests (NDT)

4.9. Sonic Logging Tests

4.9.1.1 Sonic Logging Tubes

Provide sonic logging tubes cast into piles selected for sonic logging tests.

The tubes are to be manufactured from steel and extend 0.2 m to 0.5 m above the pile head and 0.2 to 0.5 m above the pile toe. The tubes are to have an internal diameter not exceeding  50  mm,  except  for  one  tube  in  each  pile,  which  is  to  be  of  internal diameter100 mm in order to allow for coring of the concrete at the base of the pile.

Provide three tubes for piles up to 800 mm in diameter and four tubes for piles above800 mm in diameter.

4.9.1.2 Coring

At least 7 days after the pile has been cast, but before carrying out any sonic logging test, take a core of concrete and soil or rock from the founding material.

Take the core from the base of the 100 mm diameter sonic logging tube using a triple tube core barrel. The core is to have a minimum diameter of 50 mm.

Keep the core in a suitable wooden box with depths clearly recorded on rigid markers, and photograph it along with a scale and colour chart. Thereafter, deliver these to a designated core store.

 Scan the pile toe for its integrity by measuring the propagation time of transmitted waves between the vertical tubes and the pile toe/ founding strata.

4.9.1.3 Sonic Logging Test Procedure

Carry out the following operations in sequence:

a.        Fill the tubes with water.

b.        Insert the probes into an adjacent pair of tubes and mount the drum over the pile.
Lower the probes to the bottom of the pile. Adjust their depths such that the delay time is minimised, i.e. they are at the same level.

c.         Slowly raise the probes so that successive traces of the time between signal emission and receipt are displayed on the screen of the oscilloscope. Each time the screen is filled, take a "Polaroid" photograph in order to provide a permanent record.

d.        Repeat the process for each pair of tubes, i.e. three runs for a pile with three tubes and six runs for a pile with four tubes.

e.        Lower one probe to the base of a 50 mm diameter tube while lower the other to the same depth in the 100 mm diameter tube. While the former probe is held in position, lower the latter probe into the cored hole to its lower limit. Obtain a record of the received signal delay time as a function of the depth of the second probe. Repeat this process with the first probe in all available tubes.

4.9. Low Strain Impact Tests

4.9.2. Preparation of Pile Heads

Refer to the requirements of Clause 4.7.1.

4.9.2. Procedures for vibration testing

a.        Connect the electrodynamics vibrator unit firmly to the centre of the pile.

b.        Connect the velocity transducer to the head of the pile near to its circumference.

c.        Drive the vibrator at constant force output through two cycles up to 500 Hz and
1000Hz.

d.        Process the signal from the velocity transducer to provide a measurement of the mechanical admittance of the pile as a function of frequency or both frequency ranges. Obtain a permanent record of the mechanical admittance.

4.9.2. Procedures for Modified Shock Test

a.        Connect a velocity transducer to the pile head.

b.        Strike the head of the pile a sharp blow with a hammer of mass approximately 2 kg, to which is attached a triggering device connected to the signal processing equipment.

c.         Process the signal from the velocity transducer to provide a permanent record of the seismic response.

d.         Transfer this response either in analogue or digital form as appropriate to a microprocessor which is to perform a fast Fourier transform on the output signal from which the relationship between mechanical admittance and frequency can be determined.

4.9.2. Procedures for simple shock tests

a.        Connect the velocity transducer to the pile head.

b.        Strike the head of the pile in a sharp blow with the hammer.

c.         Process the signal from the velocity transducer to provide a permanent record of the seismic response.

4.9. Non-Destructive Testing - Anomalous Test Results

Any  piles  with  anomalous  resultfrom  typical  non-destructive  tests  such  as  sonic logging, vibration test and modified shock tests may be rejected at the discretion of the SO, unless it can be demonstrated that the pile integrity is acceptable through proof coring.

4.10    Protection of Testing Equipment

4.10.1.1 Protection from Weather

Throughout the test period, protect all equipment for measuring load and movement from the weather.

4.10.1.2 Prevention of Disturbance

Keep construction equipment and persons who are involved in the testing process at a sufficient distance from the test to avoid disturbance to the measurement apparatus.

4.11    Noise and Disturbance

Carry  out  the  work  in  such  a  manner  as  to  minimise  noise,  vibration  and  other disturbance.
Comply with all current regulations and environmental controls.

No comments:

Post a Comment