2. PERFORMANCE REQUIREMENTS
2.1
Requirements for Design Verification
The required working load and sizes of the piles are indicated in the drawings, together
with an indication of the required
pile penetration depth.
Based on actual ground conditions encountered as revealed by boring logs or ground
investigations, carry out design check to confirm the required pile length as to achieve
the specified working
load
within
the
specified limits for load settlement behaviour
as indicated in Clause
2.2. Account for effects of negative
skin friction where applicable.
Verify the design
based on SS CP 4 unless otherwise agreed.
2.2 Performance Criteria for Bored Piles
Any of the piles,
when under static or dynamic
load test, is to satisfy
the performance criteria as set out below:
Axial Compression Tests (Ultimate and Working Load)
Pile Type
and Size
|
Specified
Working Load (Axial Compression)
|
Permitted Settlements (mm)
|
|||
(SWL)
(kN)
|
1.0*SWL
(2nd cycle)
|
1.5*SWL
(2nd cycle)
|
2.0*SWL
(2nd cycle)
|
Residual
Settlement
(End of 2nd
cycle)
|
|
900mm
diameter
Bored Pile
1200mm
diameter Bored Pile
|
4550
8500
|
7
7
|
15
15
|
25
25
|
7
7
|
In addition, the overall
pile capacity in ultimate
load tests is to have
factors of safety of at
least 2.5 against design ultimate compression
load, 2.0 against design ultimate lateral
load and 3.0 against design
ultimate tension load.
2.3 Permissible Damage
Criteria for Existing
Critical Structure or Services
Based on the results of the damage assessment as set out in Clause 1.4.2, propose
the allowable ground settlement and vibration limits due to the works taking into account the vulnerability and sensitivity
of
the
adjacent
properties
e.g.
VLCC
(48”
Crude Oil Pipelines).
State the values for alert and work suspension
levels in the submission in accordance
with the requirements of Building
Control Act [Section
7(2)] Annex (BE/CP/5).
Notwithstanding the above, ensure
that the ground movements and vibrations
generated by the works comply
with the following if more stringent:
NPQS
C4-10 Bored Piling Piles
a. Generally comply with the requirements of BS 5228 Part 1.
b. The vibration generated by the works in MRT structures not to exceed a peak
particle velocity of 15mm/s.
c. Unless otherwise directed, refer to Section C2-50, Clause 4.2.2
for general
restrictions
on ground movements
and vibration
limits
for adjacent structures where relevant.
d. Refer
to
piling drawings for vibration limits.
No comments:
Post a Comment